Preservation Projects

Xでポスト
フェイスブックでシェア
ラインでシェア

Article ID 1009933 

PrintPrint in large letters

The Atomic Bomb Dome has remained in the condition it was left in after the bombing. There have been no significant structural changes, but as the Dome continued to deteriorate due to wind and rain, the structure was faced with the possibility of collapse. This led to a preservation project conducted in FY1967 to preserve the Dome as it was after the bombing. Four additional preservation projects have been conducted since.

Fundraising campaigns were conducted to raise the construction fees for both projects, gathering a large amount in donations. The remainder of the funds were reserved in the Atomic Bomb Preservation Project Fund and used for the third, fourth, and fifth preservation projects and preservation surveys.

Below is a summary of past construction work.

Preservation Projects

Preservation Project

Period

Basic Aims

Construction Summary

I April to August 1967 Preserve the building in its existing state, including the parts that had caved in or fallen apart
  • Seal cracks on the walls
  • Reinforce unstable parts with steel framework
  • Raise walls, pull up girders, pile up collapsed bricks
  • Apply anti-corrosion coating to the original steel frame and new reinforcements
  • Waterproof storehouse roof, reinforce wall tops with mortar
II October 1989 to March 1990 Prevent the further deterioration of concrete, bricks, and other materials as well as those which were added during the first preservation project
  • Repair deteriorating concrete
  • Repair brickwork
  • Apply anti-corrosion coating to steel frame
  • Replace corroded parts of the original steel frame
  • Apply water repellant to all wall surfaces
III October 2002 to March 2003 Prevent further deterioration of the structure caused by rain water
  • Rain damage prevention
    (wall tops, windowsills, interior walls inside the dome, former storehouse, and basement)
  • Apply coating to steel reinforcements
  • Preservation measures for the ceiling slabs of the former storehouse
IV November 2015 to July 2016 Prevent further damage caused by earthquakes
  • Earthquake damage prevention (Adding steel reinforcements on three walls)
V June 2020 to April 2021 Prevent further deterioration of the steel components
  • Repaint steel rafters and steel reinforcements
  • Repair brickwork
  • Repair window frames
  • Repair metal reinforcements

Detailed summaries of preservation work

Inquiries regarding this page

Park Development Division, Greenery Promotion Department, Urban Development Bureau
Phone: 082-504-2393 / Fax: 082-504-2391
Mail: [email protected]